Canada’s two seasons, Winter, and “Construction” are an adage almost everywhere, and Mississippi Mills is no exception.
The Town’s surface treatment program is continuing ahead of schedule, with the 8th Concession North Pakenham and 12th Concession South Pakenham (Darks Side Road to Kinburn Side Road) jobs completed.
Staying on the Darks Side, the portion from Kinburn Side Road to the municipal limits is alos done.
Slated to be finished the week of August 11th are two portions on Rae Road. (County Road 29 to 8th Concession Ramsay, and 4th Concession Ramsay to 5th Concession Ramsay).
Future projects up for resurfacing include: Water Street (Bridge Street to end of roadway); ?? Townline Road West (Highway 7 to municipal limits) and Pick Road (County Road 29 to 8th Concession Ramsay).
Watch for construction signage and detour information in these areas. Please slow down for crews.
By Rick Stow